Imperial County is providing an update regarding the temporary moratorium on final County approvals for data center facilities in unincorporated areas.
In June 2026, the Imperial County Board of Supervisors adopted a 45-day temporary moratorium to allow additional time to consider issues associated with data center development. The Board also established the Data Center Advisory Committee to provide a forum for community input and to develop recommendations regarding potential policies and regulations.
Following a public hearing in July, the Board extended the temporary moratorium for an additional ten months and fifteen days.
The Imperial County Superior Court recently ruled that the findings supporting the moratorium did not sufficiently address all applicable requirements under state law and directed that the moratorium be set aside.
The County respects the court’s ruling and is reviewing the decision and its next steps.
The County’s broader effort to evaluate data center development will continue. The Board of Supervisors remains committed to hearing from residents, stakeholders, and the Data Center Advisory Committee as the County considers appropriate policies related to future data center development in Imperial County.
Additional information regarding the Data Center Advisory Committee and opportunities for public participation will continue to be made available through official County communication channels.